Project Approved at FCC 3/16/2022
City of Fernley
Engineering Department
Kari Weitzel
kweitzel@cityoffernley.org
775-784-9866
Design Firm : CFA
Contractor: A & K Earth Movers
Inspector: CME
Project Start Date: Spring/Summer 2022
This project includes a new 28' Gazebo, new bathroom facility, a walking path that runs through out the park. The small and large dog park will each get one 12' gazebo. The north side of the park with be constructed with ADA sidewalks, along with other minor improvements.