This week ( April 4th - April 8th ) we start crack sealing and wide crack repair. Click on the link below to see streets receiving treatment this week.
Pavement Crack Sealing and Wide Crack repair schedule as follows:
Schedule 4.4 Crack Seal- Highlighted streets in the Donner Trails Subdivision.
When: Monday, April 4th, 2022
Schedule 4.5 Crack Seal- Highlighted streets in Donner Trails Subdivision.
When: Tuesday, April 5th, 2022
Schedule 4.6 Crack Seal- Highlighted streets in Donner Trails Subdivision
Schedule 4.6 Wide Crack Repair - Highlighted streets in Donner Trails Subdivision & Silverland Subdivision
When: Wednesday, April 6th, 2022
Schedule 4.7 Crack Seal - Highlighted streets in Donner Trails Subdivision
Schedule 4.7 Patch Repair - Highlighted Streets in Silverland Subdivision & Sierra Vista Subdivision
When:Thursday, April 7th, 2022
Schedule 4.8 Crack Seal- Highlighted streets in Silverland Subdivision & Hardie Ln
Schedule 4.8 Wide Crack Repair - Highlighted streets in Donner Trails Subdivision & Sierra Vista
When: Friday, April 8th, 2022
Schedule 4.5 Crack Seal
Schedule 4.6 Crack Seal
Schedule 4.6 Wide Crack Repair
Schedule 4.7 Crack Seal
Schedule 4.7 Patching
Schedule 4.8 Crack Seal
Schedule 4.8 Wide Crack Repair