Weekly Update April 11th - 15th

This week ( April 11th - April 15th ) we continue to crack seal , wide crack repair, and pavement patching .

The schedule is as follows:

Schedule CS 4-11 Crack Seal- Highlighted streets in the Desert Lakes Subdivision.

Schedule WCR 4-11 Wide Crack Repair - Highlighted streets in the Donner Trails Subdivision.

When: Monday, April 11th, 2022

Schedule PATCH 4-12 Patch Repair- Highlighted streets in Donner Trails Subdivision.

Schedule WCR 4-12 Wide Crack Repair- Highlighted streets in Donner Trails Subdivision.

When: Tuesday, April 12th, 2022

Schedule PATCH 4-13 Patch Repair- Highlighted streets in Donner Trails Subdivision.

Schedule CS 4-13 Crack Seal- Highlighted streets in the Desert Lakes Subdivision.

When: Wednesday, April 13th, 2022

Schedule PATCH 4-14 Patch Repair- Highlighted streets in Donner Trails Subdivision.

When:Thursday, April 14th, 2022

Schedule PATCH 4-15 Patch Repair- Highlighted streets in Sierra Vista Subdivision.

When: Friday, April 15th, 2022

UPDATE: 
Rescheduled work for April 11th and April 12th due to weather conditions
Schedule 4.11 - 4.15 5
Schedule 4.11 - 4.15 8
Schedule 4.11 - 4.15 6
Schedule 4.11 - 4.15 1
Schedule 4.11 - 4.15 7
Schedule 4.11 - 4.15 2
Schedule 4.11 - 4.15 3
Schedule 4.11 - 4.15 4