[ARCHIVED] Cottonwood Lane Reconstruction Project Update: Construction Week 2/27 thru 3/3/2023

9903.000_COTTONWOOD SCHEDULE 3.1-3.3.202

Cottonwood Lane Reconstruction Project Update

Please see the below exhibits for the week of March 1st - March 3rd, 2023.

No construction for Monday, February 27th and Tuesday, February 28th due to weather.

Exhibit No. 1

BEGINNING WEDNESDAY, MARCH 1ST SIERRA NEVADA CONSTRUCTION WILL BE CONDUCTING JACK & BORE OPERATIONS ON US50A/95A AT COTTONWOOD LANE.

WORK ZONE: 3/1 THROUGH 3/3/2023. WORK HOURS: 7:00 AM TO 4:30 PM TO FACILITATE THE TIMELY COMPLETION OF THIS WORK, THE SOUTHBOUND SHOULDER WILL BE CLOSED ON US50A/95A AT COTTONWOOD LANE. 

Exhibit No. 2

BEGINNING WEDNESDAY, MARCH 1ST SIERRA NEVADA CONSTRUCTION WILL CONTINUE INSTALLING SEWER & WATER IMPROVEMENTS ON COTTONWOOD LANE BETWEEN HARDIE LANE & US50A/95A. 

WORK ZONE: 3/1 THROUGH 3/3/2023. WORK HOURS: 7:30 AM TO 4:30 PM. TO FACILITATE THE TIMELY COMPLETION OF THIS WORK, TRAFFIC WILL BE LIMITED TO EASTBOUND ONLY TRAVEL BETWEEN US50A/95A & HARDIE LANE. WESTBOUND TRAFFIC WILL BE DETOURED AT HARDIE LANE TO SHADOW LANE TO US50A/95A.  

Exhibit No. 3

BEGINNING WEDNESDAY, MARCH 1ST SIERRA NEVADA CONSTRUCTION WILL BE INSTALLING CONCRETE IMPROVEMENTS ON COTTONWOOD LANE BETWEEN COOK WAY & FARM DISTRICT ROAD. 

WORK ZONE: 3/1 THROUGH 3/3/2023. WORK HOURS: 7:00 AM TO 4:30 PM. 

TO FACILITATE THE TIMELY COMPLETION OF THIS WORK, TRAFFIC WILL BE LIMITED TO WESTBOUND ONLY TRAVEL BETWEEN COOK WAY & FARM DISTRICT ROAD. EASTBOUND TRAFFIC WILL BE DETOURED AT COOK WAY TO CRIMSON ROAD TO RICCI WAY TO WILSON WAY TO FARM DISTRICT ROAD. 

FLAGGERS WILL BE PROVIDED DURING PEAK PERIODS TO ASSIST PEDESTRIAN & VEHICLE TRAFFIC TO NAVIGATE THE WORK ZONE.

Please choose your travels with this in mind and take an alternate route if possible.

Remember to drive slowly through the construction zone while our contractors work diligently to complete this portion of the project.

Thank you,

Engineering Department

EXHIBIT NO. 1

9903.000_COTTONWOOD SCHEDULE 3.1-3.3.202

EXHIBIT NO. 2

9903.000_COTTONWOOD SCHEDULE 3.1-3.3.2023-2

EXHIBIT NO. 3

9903.000_COTTONWOOD SCHEDULE 3.1-3.3.2023-3