Posted on: April 10, 2023

[ARCHIVED] Cottonwood Lane Reconstruction Project Update: Construction Week 4/10 - 14/2023

EXHIBIT 1

BEGINNING MONDAY APRIL 10th SIERRA NEVADA CONSTRUCTION WILL BE INSTALLING CONCRETE IMPROVEMENTS ON COTTONWOOD LANE.

WORK ZONE: 4/10 THROUGH 4/14/2023. WORK HOURS: 7:00 AM TO 4:30 PM 

TO FACILITATE THE TIMELY COMPLETION OF THIS WORK, TRAFFIC WILL BE AS FOLLOWS: COTTONWOOD LANE (COOK WAY TO BARDOT WAY) 4/10-4/14/2023: SHOULDER CLOSURES WILL BE PRESENT THROUGHOUT THE WORK ZONE. TWO-WAY TRAFFIC WILL BE MAINTAINED DURING ALL SHOULDER CLOSURES. 

EXHIBIT 2

BEGINNING MONDAY, APRIL 10th SIERRA NEVADA CONSTRUCTION WILL CONTINUE INSTALLING SEWER & WATER IMPROVEMENTS ON COTTONWOOD LANE BETWEEN HARDIE LANE & US50A/95A.

WORK ZONE: 4/10 THROUGH 4/14/2023. WORK HOURS: 7:30 AM TO 4:30 PM 

TO FACILITATE THE TIMELY COMPLETION OF THIS WORK, TRAFFIC WILL BE LIMITED TO EASTBOUND ONLY TRAVEL BETWEEN US50A/95A & HARDIE LANE. WESTBOUND TRAFFIC WILL BE DETOURED AT HARDIE LANE TO SHADOW LANE TO US50A/95A. 

EXHIBIT 1

9903.000_COTTONWOOD SCHEDULE-PCC_04.10.2023

EXHIBIT 2

9903.000_COTTONWOOD SCHEDULE_04.10.2023-2